Warning: strtotime(): It is not safe to rely on the system's timezone settings. You are *required* to use the date.timezone setting or the date_default_timezone_set() function. In case you used any of those methods and you are still getting this warning, you most likely misspelled the timezone identifier. We selected 'America/Montevideo' for 'UYST/-2.0/DST' instead in /var/www/incoci.com.uy/html/incoci/libraries/joomla/utilities/date.php on line 56 Warning: date(): It is not safe to rely on the system's timezone settings. You are *required* to use the date.timezone setting or the date_default_timezone_set() function. In case you used any of those methods and you are still getting this warning, you most likely misspelled the timezone identifier. We selected 'America/Montevideo' for 'UYST/-2.0/DST' instead in /var/www/incoci.com.uy/html/incoci/libraries/joomla/utilities/date.php on line 198

Puente sobre el Río Santa Lucía

  • Contratante: CORPORACIÓN VIAL DEL URUGUAY - MTOP
  • Obra: Ruta 11 – Nuevo Puente sobre el Río Santa Lucía,  Consorcio Teyma - INCOCI.
  • Años: 2011 - en ejecución
  • Monto del contrato (sin IVA): US$ 4.330.511,00
  • Comentarios:
    - El presente contrato tiene como objeto el proyecto y construcción de un nuevo puente insumergible sobre el Río Santa Lucía en una variante de trazado de la Ruta 11 en las proximidades de la Ciudad de Santa Lucía.
    - Estos trabajos comprenden el proyecto ejecutivo de la estructura y de construcción del un nuevo puente. El mismo tendrá 650 m de longitud mínima con 10.20 m de ancho de calzada.
    - Longitud del puente: 650 m por 10.20m de ancho.